LONG Huihu. Key Technology for Excavation of Main Access Tunnel of a Hydropower Station in East Africa[J]. Intelligent Building and Construction Machinery, 2021, 3(12): 19-21.
Citation: LONG Huihu. Key Technology for Excavation of Main Access Tunnel of a Hydropower Station in East Africa[J]. Intelligent Building and Construction Machinery, 2021, 3(12): 19-21.

Key Technology for Excavation of Main Access Tunnel of a Hydropower Station in East Africa

  • Received Date: 2021-10-18
  • Rev Recd Date: 2021-12-21
  • Available Online: 2022-03-28
  • Publish Date: 2021-12-28
  • The main access tunnel of a hydropower station in East Africa is the main transportation channel of the hydropower station. The tunnel is long, the net section is wide, and the geological and hydrological environment is poor, so that the excavation construction is difficult and the safety risk is high. In this regard, combined with the construction practice of the project, this paper makes a detailed discussion on the key technologies of the excavation and construction of the main access tunnel into the plant, for reference.

     

  • loading
  • [1]
    陈文亮.猴子岩水电站进厂交通洞洞口段施工技术研究[D].成都:西南交通大学,2017.
    [2]
    李向超.向家坝水电站南总干渠上穿水富交通隧洞开挖方式及质量控制[J].水利水电技术,2016(s2):56-59.
    [3]
    杨晓辉.某电站交通洞土洞进洞技术分析[J].工程技术研究,2019,4(21):173-174.
    [4]
    达玫 . 小浪底引黄工程地下泵站交通洞洞口施工方案设计[J]. 山西水利 ,2017(7):46-47+49.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (93) PDF downloads(0) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return