Volume 3 Issue 3
Mar.  2021
Turn off MathJax
Article Contents
ZHANG Qiang. Analysis on the Treatment Technology of Residual Slope Soil, Karst and Unbiased Pressure Tunnel Opening[J]. Intelligent Building and Construction Machinery, 2021, 3(3): 28-30.
Citation: ZHANG Qiang. Analysis on the Treatment Technology of Residual Slope Soil, Karst and Unbiased Pressure Tunnel Opening[J]. Intelligent Building and Construction Machinery, 2021, 3(3): 28-30.

Analysis on the Treatment Technology of Residual Slope Soil, Karst and Unbiased Pressure Tunnel Opening

  • Received Date: 2021-02-05
  • Publish Date: 2021-03-28
  • The upward slope at the entrance of the Lianhuashan Tunnel is relatively steep and biased, and the lower layer of the slope is loose accumulation of soil. The geological conditions are complicated. During the construction of the excavation tunnel, it is easy to slip and collapse in case of rain. There are hidden safety hazards in the construction and operation. The lower part of the tunnel foundation is now gray. Rock and karst; reinforcement by bolt grouting, consolidation and reinforcement by anchor cable frame measures, open tunnel backfi lling and double-row anti-slide pile reinforcement measures to eliminate the infl uence of bias, and double-wall tunneling technology to ensure tunnel entry Safety: The operation safety is ensured by extending the open tunnel, using pile foundation reinforcement measures for the base, and adopting open curtain protection nets for the side slope.

     

  • loading
  • [1]
    中铁铁路总公司.关于《南平至龙岩铁路扩能工程设计安全评估报告》的函(鉴线函[2012]22号)[M].北京:中铁铁路总公司,2012.
    [2]
    国家发改委.关于福建省南平至龙岩铁路扩能工程可行性研究报告的批复(发改基础[2013]306号)[M].北京:国家发改委, 2013.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (171) PDF downloads(1) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return