Analysis of Common Problems and Solutions in Expressway Pumping Concrete Construction
-
摘要: 针对高速公路施工中用于桥涵施工的泵送混凝土在泵送过程中容易出现堵泵、难泵等现象,本文对其原因进行了相关分析,阐述了施工过程中实际解决方法,为后续施工积累经验教训。避免施工中再次出现类似问题或出现问题后难以解决,延误工程进度。Abstract: Aiming at the phenomenon of pumping concrete used for bridge and culvert construction in expressway construction, which is prone to block pumping and difficult pumping during the pumping process, this article analyzes the reasons for it, expounds the actual solution during the construction process, and provides a follow-up Accumulate experience and lessons during construction. Avoid recurrence of similar problems during construction or difficulty in solving problems after they occur, which will delay the progress of the project.
-
Key words:
- pumping concrete /
- blocking the pump /
- admixture /
- slump /
- raw materials
-
[1] A.M.内维尔.混凝土的性能[M].北京:中国建筑工业出版社,2011(4):288-289. [2] 乔运鹏.泵送混凝土使用中应注意的问题[J].建筑与工程,2006(5):99.