Discussion on Gas Control Measures in the Outlet Section of Sanyangxi Water Intake Tunnel of Shaba Reservoir in Sinan County
-
摘要: 在我省的中小型水利工程隧洞施工中,遇到瓦斯的情况并不多见,因此一旦遇到后可以提供借鉴的治理程序和方式也不充裕。通过沙坝水库三洋溪隧洞从发现瓦斯到委托检测、选定单位、实施治理、验收合格的整个过程进行分析,不仅确保了程序合规,实施过程安全,并且还降低投资,给后期其他中小型水利工程遇到类似问题提供了较为完整的经验。Abstract: In the construction of tunnels of small and medium water conservancy projects in our province, it is rare to encounter gas. Therefore, once encountered, there are not enough treatment procedures and methods that can be used for reference. Through the analysis of the entire process from the discovery of gas to the commissioned inspection, the selection of units, the implementation of treatment, and the acceptance of the Sanyangxi Tunnel of the Shaba Reservoir, it not only ensures the compliance of the procedures, the safety of the implementation process, but also reduces the investment. Water conservancy projects encountered similar problems and provided a relatively complete experience.
-
Key words:
- shaba reservoir /
- tunnel /
- gas /
- detection /
- treatment
-
[1] 杨汉铭,赵德才,夏云东.水打桥隧洞煤与瓦斯突出段专项治理实践[J].水利水电快报,2019(6):73-75.
点击查看大图
计量
- 文章访问数: 36
- HTML全文浏览量: 15
- PDF下载量: 1
- 被引次数: 0